What this video covers

Follow the installation workflow for a single-phase TSP protecting equipment control power. The guide covers horizontal and vertical mounting, INPUT and OUTPUT connections, protective earth, both terminal covers, power-up and commissioning.

This video explains the installation workflow. Actual work must be performed by qualified personnel using the current manual for the specific model and approved site procedures.

Read the video transcript

Spoken content from the finalized captions for this published video. Subtitle line breaks have been joined for readability.

  1. 00:00

    This single-phase TSP protects equipment control power. Let's start with horizontal mounting.

  2. 00:07

    Check the ratings on the product label.

  3. 00:10

    The input and output connections stay the same when mounted vertically.

  4. 00:16

    Turn off power to the circuit before installation.

  5. 00:27

    Open the rear terminal cover to see the connections.

  6. 00:31

    Identify the input, output and protective earth cables.

  7. 00:37

    Connect the incoming supply cable to the TSP input terminals.

  8. 00:43

    Align the ring terminal with the screw and secure it.

  9. 00:48

    Match P and N to the correct input terminals.

  10. 00:52

    Connect the equipment's power cable to the TSP output terminals.

  11. 00:57

    Match P and N on the output side too.

  12. 01:02

    Connect protective earth to the far-right earth terminal.

  13. 01:06

    The output cable connects to the equipment's control power input.

  14. 01:11

    Check the wiring, then fit the terminal cover.

  15. 01:16

    You can connect a laptop if the communications option is fitted.

  16. 01:24

    Fit the metal protective cover and fasten it securely.

  17. 01:33

    Turn on the dedicated TSP input branch breaker.

  18. 01:38

    Turn on the rear power switch.

  19. 01:44

    Check the display for full charge. The green standby light means TSP is ready to provide protection.

  20. 01:52

    Now check that control power and the process are operating normally.

  21. 01:56

    With the process running, cycle the input branch breaker off and on within one second. Confirm control power and the process continue.

  22. 02:06

    With optional communications, check events and input and output waveforms on the laptop. This screen is an example from the manual.

  23. 02:17

    We'll explain the normal indicators and how to check event history. Contact WESCO anytime if you have questions.

  24. 02:23

    Thank you.